Complete production line installation

AZH project-managed the installation of a complete 225-metre production line for a prestigious alcoholic beverage producer.

AZH’s scope

Engineering and delivery.

AZH managed all lift-and-shift activities and the ingress of the machinery, alongside mechanical and electrical installation, system integration and commissioning. The line included a front-end cap feed system; an empty-bottle de-shrouding machine with hydraulic baler; a depalletiser; accumulation conveyors; a combined rinser, filler and capper; a labeller; Dynac accumulation spirals; a casepacker with automated blank feeding; a high-level palletiser; pallet conveyors; and a pallet wrapper.

Delivery

Project outcome.

The 225-metre line was installed as an integrated production system, with its machinery and conveying equipment coordinated through to commissioning and handover.

Need similar support?

Talk to AZH about your project.

Discuss installation, relocation, integration or commissioning support.

Contact AZH Engineering

info@azhengineering.co.uk

+44 7789 958426